Description
Law and Practice of CONSTRUCTION CONTRACTS by CHOW KOK FONG
LLB.(HONS), B.Sc.(BLDG)(HONS), M.BA, F.R.I.C.S., F.C.I.S., F.C.I.ARB., F.S.I.ARB., F.S.PROJ.M.
Review by marceljude.ai
I read the book. Chow Kok Fong’s Law and Practice of Construction Contracts, treating the work not merely as a construction-law manual, but as a doctrinal map of how construction contracts are made, priced, administered, breached, certified, disputed, and finally resolved.
The book is especially strong because it does not separate “law” from “practice.” Its central insight is that construction law is not just contract doctrine applied to buildings; it is a special commercial environment where tendering, certification, progress payment, variations, delay, ground risk, bonds, sub-contracting, negligence, litigation, arbitration, and negotiation all interact. The foreword describes the work as covering “almost every conceivable aspect” of construction contracts and notes its attention to claims, certification, performance bonds, litigation, and arbitration. The author’s preface also identifies the core of the book as variations, adverse soil conditions, delays, termination, nominated subcontractors, and negligence, with added treatment of pre-contract issues, payment certificates, and performance bonds.
Contents and page map
The book opens with preliminary materials: About the Author, Foreword, Prefaces, Acknowledgments, tables of cases, legislation, and references to standard forms. The substantive work then runs through eighteen chapters, a postscript, two appendices, and an index. The main chapters and actual book page starts are:
Chapter 1, General Principles, page 3.
Chapter 2, Construction Contract Models and Standard Forms, page 51.
Chapter 3, Pricing and Claim Practices, page 92.
Chapter 4, Redress for Breach of Contract, page 115.
Chapter 5, Claims for Variations, page 175.
Chapter 6, Variations Arising from Ground Conditions, page 247.
Chapter 7, Valuation of Variation Claims, page 295.
Chapter 8, Payments and Certification, page 335.
Chapter 9, Time-Related Claims, page 376.
Chapter 10, Computation of Time-Related Claims, page 469.
Chapter 11, Performance Bonds, page 524.
Chapter 12, Claims Arising from Termination, page 555.
Chapter 13, Matters following Termination, page 623.
Chapter 14, Sub-contractor and Suppliers, page 646.
Chapter 15, Claims under Negligence, page 721.
Chapter 16, Construction Litigation, page 802.
Chapter 17, Arbitration, page 870.
Chapter 18, Preparation and Negotiation of Claims, page 937.
Postscript, The Public Sector Standard Conditions of Contract, page 972.
Appendix 1, Articles of Agreement and Conditions of Contract of the Singapore Institute of Architects, page 989.
Appendix 2, Singapore Public Sector Conditions of Contract, page 1057.
Index, page 1125.
Entire-book review
This book is best understood as a bridge between the lawyer’s contract doctrine and the construction professional’s project reality. It begins with formation of the contract, then moves through models and standard forms, pricing, breach, variations, ground conditions, valuation, certification, delay, bonds, termination, subcontracts, negligence, litigation, arbitration, and negotiation. That sequence is pedagogically sound: it mirrors the life cycle of a construction project, from tender to claim resolution.
As a law professor, I would describe the book’s method as case-driven but industry-conscious. The author rarely treats cases as abstract authorities. Instead, cases are used to explain what actually happens on projects: tenders are qualified, letters of intent are used before formal contracts are signed, drawings conflict with bills, architects certify under pressure, contractors front-load prices, sub-contractors depend on main contractors for payment, ground conditions differ from reports, and performance bonds can become instruments of commercial leverage.
Its strongest intellectual contribution is the insistence that construction contracts are risk-allocation instruments. The book repeatedly asks: Who should bear the risk of defective documents? Unexpected ground conditions? Delay? Wrong certification? Insolvency? Non-payment? Subcontractor failure? Defective design? The answer is never merely “the law says so”; it depends on contract wording, standard form structure, commercial expectation, and the institutional role of certifiers, architects, engineers, quantity surveyors, banks, courts, and arbitrators.
Its Singapore focus is also important. The book does not simply import English law. It studies where Singapore law follows English common law and where it departs from it. The most striking example is performance bonds: English law traditionally restricts restraint mainly to fraud, while Singapore recognises unconscionability as a separate basis for restraining abusive calls on bonds. The book also gives major attention to the SIA form and the Public Sector Standard Conditions of Contract, making it unusually valuable for Singapore and regional practice.
Its limitation is also part of its strength: the work is dense and practitioner-oriented. A student reading it casually may be overwhelmed by the number of standard forms, clauses, cases, and claim categories. But for serious construction-law study, that density is beneficial. Construction law is not a subject where elegant general principles alone are enough; the commercial consequences are hidden in certificates, notices, valuation rules, delay analyses, and dispute procedures.
Chapter 1: General Principles — page 3
Chapter 1 lays the legal foundation for the whole book. It introduces the development process, tendering, contract documents, express and implied terms, indemnities, warranties, and mistake. The chapter’s value is that it makes clear from the start that construction contracts are not ordinary sales transactions. They involve a long process, multiple actors, evolving documentation, and a project that is physically created over time.
The Development Process — page 3.
This section identifies the principal players: developer or client, consultants, and contractor. The legal significance is that construction obligations are distributed through a network rather than a simple two-party exchange. Architects, engineers, quantity surveyors, and specialist consultants shape the project before the contractor performs it. Planning and building permits show that statutory control is part of the contractual setting. Placement of the contract explains tendering or negotiation as the point at which design becomes contractual obligation. Construction operations and handing over show why completion, defects, and maintenance periods later become major legal issues.
Tenders and Award of Contract — page 6.
This is a strong section because it explains that a tender is generally an offer, while an invitation to tender is not itself an offer. The subsections on tenders as offers, qualifications, evaluation, acceptance, letters of intent, consideration, and formation show that construction contracts often form gradually rather than by a single neat act. The discussion of letters of intent is especially practical: they may look informal, but they can create legal consequences if parties act on them. The section also warns that post-tender negotiations and “subject to contract” language can complicate formation.
Features of a Construction Contract — page 23.
The comparison with sale of goods transactions explains why construction law needs special treatment. A construction contract is not just the delivery of a finished object; it involves progress payments, variations, supervision, certification, and ongoing risk management. The subsections on progress payments and variation provisions are crucial because they become the backbone of later chapters.
Contract Documents — page 26.
This section explains the legal importance of the articles of agreement, conditions of contract, drawings, bills of quantities, preliminaries, trades bills, provisional sums, pricing summaries, schedules of rates, and specifications. Its deeper point is that a construction contract is a bundle of documents, and disputes often arise because those documents do not speak with one voice. A law professor would stress this as a lesson in documentary hierarchy and interpretation.
Express Terms — page 33.
The chapter then turns to express terms and rules of interpretation, including literal interpretation, contra proferentem, ejusdem generis, and incorporation of terms. This is doctrinally orthodox but practically important. Construction disputes often turn on whether a term has been incorporated or whether a clause has been drafted clearly enough to shift risk.
Implied Terms — page 37.
The implied-terms discussion is useful because construction contracts cannot anticipate every event. The subsections cover principles, construction examples, statutory terms, the Sale of Goods Act 1979, the Supply of Goods and Services Act 1982, and parol evidence. The chapter correctly places implied terms in tension with express drafting: courts may imply terms for business efficacy, but they will not rewrite commercial bargains.
Indemnities and Warranties — page 43.
The explanation of purpose, nature, and common-law distinction is practical. Indemnities and warranties are common in specialist works, defects, waterproofing, façade work, and design obligations. The chapter explains why their wording matters: an indemnity may operate differently from a warranty in timing, proof, and remedies.
Mistake in Law and Equity — page 45.
The subsections on common mistake, unilateral mistake, and mistake in construction contracts close the chapter by showing that formation can be attacked where parties are wrong about a fundamental matter. In construction, mistake may arise from quantities, site conditions, documents, or assumptions at tender stage. The book’s treatment is cautious: mistake is not a general escape from a bad bargain.
Chapter 2: Construction Contract Models and Standard Forms — page 51
Chapter 2 is one of the book’s most important structural chapters. It explains why standard forms exist and how different project models allocate responsibility differently. The central lesson is that no construction contract form is neutral. Every form carries assumptions about design responsibility, certification, price, risk, and dispute handling.
Development of Standard Forms — page 51.
The genesis section shows that early construction contracts were often loosely framed, producing disputes over what the contractor had actually promised. The case for standard forms is therefore not merely convenience; it is legal risk reduction. General application issues remind readers that standard forms must still be matched carefully to project type and amended intelligently.
Contractual Models — page 53.
The book reviews traditional building contracts, engineering contracts, design-and-build, fee-based models, management contracting, construction management, and term contracts. The traditional model separates design from construction: the employer appoints consultants, and the contractor builds. Design-and-build shifts more responsibility to the contractor. Management contracting and construction management reallocate cost and coordination risk. Term contracts suit repeated work or maintenance. This section is excellent because it teaches that legal obligations follow commercial architecture.
Choice of Standard Forms — page 67.
The discussion covers building projects, JCT forms, employer amendments, civil engineering projects, ICE conditions, FIDIC, the New Engineering Contract, design-and-build forms, public sector projects, industrial/process plants, and related standard forms. The professor’s point is that form selection is a legal strategy. Choosing JCT, ICE, FIDIC, SIA, PSSCOC, or a design-and-build form affects claims, valuation, certification, and dispute resolution.
Singapore Institute of Architects Standard Form — page 83.
This section is particularly important to Singapore construction law. It reviews development of the SIA form, the Wallace drafting rationale, versions of the contract, guidance notes, obligations of parties, all-inclusive price formulation, removal of loss-and-expense provisions, additional contractor submissions, temporary finality, and minor works. The concept of temporary finality is especially powerful: certificates may not be finally binding forever, but they can have immediate interim effect for cash-flow purposes.
Chapter 3: Pricing and Claim Practices — page 92
Chapter 3 moves from formation and form selection into the economics of construction contracting. Its key lesson is that pricing is never merely arithmetic. Pricing decisions later become claims, disputes, and evidential problems.
Introduction — page 92.
The chapter frames pricing as connected to contractual models. Bills of quantities may suit traditional contracting, while cost-based arrangements may suit management contracting. This is useful because the same project facts may produce different claims depending on pricing structure.
Pricing of Bills of Quantities — page 92.
The subsections explain trade bills, basic pricing, application of prices to variations, preliminaries, fixed-cost items, recovery of preliminaries for quantity differences, and time-dependent items. The legal significance is that bills of quantities are not just descriptions of work; they are the pricing machine. A variation claim often succeeds or fails depending on how the relevant work was priced in the bills.
Alternative Pricing Arrangements — page 96.
The section covers lump-sum contracts, work exceeding the contractor’s estimate, price adjustment for variations, fixed schedules of rates, and cost-based contracts. The contrast between lump-sum and remeasurement approaches is central. In a lump-sum contract, the contractor may bear more risk for quantities; in a remeasurement contract, actual quantities may drive payment.
Pricing Errors — page 98.
The subsections on computational errors, pricing redistributions, and deliberate pricing errors are excellent practice material. They show that a tender error may not automatically excuse the contractor. The section also illustrates why tender review before award is legally and commercially important.
Pricing Strategies — page 100.
The book’s discussion of front loading, claims loading, pricing qualifications, and negative rates is one of its most practical parts. Front loading improves early cash flow; claims loading anticipates variation opportunities; qualifications preserve room for adjustment; negative rates may be inserted where the contractor expects external recovery. A law professor would describe this as the chapter where the author reveals the strategic behaviour hidden behind “price.”
Claims and Payments — page 104.
This section links pricing to claims. It explains construction claims and progress payments, claims premises, breach claims, programming for claims, changes in quantity, claims under contract, performance of existing obligations, and claim quantum. The claim heads—additional expenditure, financing costs, productivity loss, site overheads, head office overheads, and loss of profit—foreshadow later delay and damages chapters.
Chapter 4: Redress for Breach of Contract — page 115
Chapter 4 is the doctrinal core of the book. It sets out what happens when contractual performance fails. The chapter is important because construction claims are often pleaded as variation claims, delay claims, or certification disputes, but beneath them lies the general law of breach, damages, mitigation, repudiation, frustration, quantum meruit, specific performance, and injunction.
Nature of a Breach of Contract — page 115.
This section defines breach as incomplete or defective performance without lawful excuse. It gives the reader a baseline: construction difficulty is not automatically a legal excuse.
Excuses for Non-Performance — page 115.
The subsections cover discharge by agreement, frustration, force majeure, illegality, and other defences. The treatment of frustration is careful: increased difficulty or expense is not enough; performance must be radically different. Force majeure is treated as a contractual rather than purely common-law device. Illegality addresses contracts affected by statute or prohibited conduct.
Consequences of a Breach — page 126.
This section explains compensation, repudiation, breaches going to the root of the contract, election to keep the contract alive, and breaches that do not discharge the contract. This is vital in construction because wrongful termination can itself become repudiatory.
Damages as a Remedy — page 133.
The subsections cover the objective of damages and direct versus consequential damages. The doctrinal centre is expectation protection: damages generally aim to place the innocent party in the position it would have occupied had the contract been performed.
Mitigation of Damages — page 138.
The duty and scope of mitigation are important in construction because a contractor or employer cannot simply let losses accumulate without reasonable steps to reduce them. This becomes crucial in delay, completion contracts, and termination.
Date for the Assessment of Damages — page 142.
The discussion of inflation, breach date, discovery date, repair date, and Singapore’s position is practical. Construction defects and delays often produce losses over time, so the assessment date can materially affect quantum.
Damages and Variations — page 149.
This short but important topic explains the boundary between contractual valuation mechanisms and damages. If a matter falls within the variation machinery, it may be valued under the contract; if it is a breach, damages principles apply.
Quantum Meruit — page 150.
The chapter explains the nature of quantum meruit, work outside contract, work done during negotiations, alternatives to damages, assessment, quality of performance, and payment agreements. This is important where work was done but the contract basis is incomplete, void, unenforceable, or outside the original scope.
Specific Performance — page 156.
The book treats this as an exceptional remedy. Construction contracts usually involve supervision and ongoing obligations, making specific performance difficult, though not impossible.
Injunction — page 159.
The section covers retention sums, repossession after termination, performance bonds, and other construction uses. The discussion is valuable because injunctions are often used to preserve position before final determination, especially where money alone is inadequate. The book notes Singapore’s special approach to restraining calls on performance bonds through fraud or unconscionability.
Legislation Affecting Redress for Breach — page 162.
The sections on misrepresentation and unfair contract terms show that statutory regimes may alter common-law outcomes. This is especially important where clauses attempt to exclude liability or where pre-contract statements influenced tendering.
Commentary on SIA Provisions — page 170.
The chapter ends by connecting doctrine to the SIA form, especially contractor obligations and remedies for defects. This is where the book’s practical strength appears again: general contract doctrine is brought back to the standard form actually used in projects.
Chapter 5: Claims for Variations — page 175
Chapter 5 is one of the central construction-law chapters. Variation claims are among the most frequent disputes in construction. The chapter’s chief strength is its insistence that a contractor must prove both authority and extra-contractual character.
Nature of Variation Provisions — page 175.
The book explains the general operation of variation clauses, the two-pronged test, and the structure of a typical provision. The two-pronged test is essential: the contractor must show a valid order and show that the work is extra, changed, or performed under different conditions.
The Power to Order Variations — page 178.
This section covers the essence of a valid variation order, who may exercise the power, the extent of the power, procedural requirements, written orders, compliance, recovery without written orders, implied promise to pay, arbitral review, constructive change, and practical issues. The legal lesson is that not every instruction is a variation. Authority and procedure matter.
Items Claimed as Variation Work — page 187.
The subsections cover what constitutes a variation, indispensably necessary work, buildability warranties, items not specifically mentioned, changes in employer requirements, contract-document claims, contractor selection of materials, omissions, discrepancies, standard method claims, quantity differences, tendering errors, statutory changes, and advice by engineers and architects. This is a detailed taxonomy of how variation disputes arise.
Limitations to the Exercise of the Power — page 216.
The book explains invalid omissions, changes affecting the scope of contract, general principles, illustrations, practice notes, effects of scope changes, and fairness. The professor’s point is that variation power is not a licence to rewrite the bargain. An omission that removes major work and gives it to another contractor may exceed the contractual power.
Commentary on SIA Provisions — page 226.
The SIA discussion covers directions, instructions, written orders, classification, inclusive price, indispensably necessary and contingently necessary work, standard method of measurement, specific variation instances, temporary works, postponement, and change of use. This is a demanding but valuable section because the SIA form uses a highly structured instruction/direction system.
Chapter 6: Variations Arising from Ground Conditions — page 247
Chapter 6 addresses one of the hardest construction-law problems: who bears the risk when the ground is not as expected? Its importance cannot be overstated. Ground conditions can transform a profitable project into a disastrous one.
Nature of the Claim — page 247.
The chapter begins by explaining why adverse ground conditions generate claims. These claims may be framed as variations, misrepresentation, breach, or contractual entitlement depending on the wording of the standard form.
Operation of Standard Form Provisions — page 253.
The book compares how standard forms allocate ground risk. This section is valuable because the legal result depends less on sympathy and more on clause wording.
Formulation Based on Foreseeability — page 255.
A foreseeability formulation asks whether an experienced contractor should reasonably have anticipated the condition. This approach protects employers against claims for risks that competent tenderers should have priced.
Policy Considerations on the Foreseeability Formulation — page 261.
This is a sophisticated section. If contractors can recover too easily, they may have little incentive to investigate or mitigate ground risk. If they cannot recover at all, tender prices rise and risk is inefficiently allocated. The book therefore treats ground-risk clauses as policy instruments, not just drafting choices.
Formulation Based on Actual Conditions — page 264.
This approach compares actual ground with stated or assumed conditions. It is more fact-driven and may favour contractors where documents conveyed a particular ground profile.
Combination Formulations — page 266.
Some contracts combine foreseeability and actual-condition approaches. The professor’s view is that such clauses must be drafted carefully or they create uncertainty.
Duty to Investigate the Site — page 268.
This section examines how far the contractor must inspect, study boreholes, review reports, and assess site risks. The legal problem is whether tender-stage information is reliable and who bears misinformation risk.
Other Aspects of Site and Soil Conditions — page 274.
This covers surrounding structures, access, groundwater, existing structures, and related physical conditions. It broadens the ground-risk question beyond soil alone.
Remedies for Misinformation — page 275.
Where tender information is misleading, possible remedies include misrepresentation, breach of warranty, negligence, or contractual relief. This section connects ground claims to Chapter 15’s negligence principles.
Notice Requirements — page 286.
Notice provisions are essential. A contractor may lose an otherwise valid claim by failing to notify in time.
Commentary on SIA Provisions — page 289.
The SIA discussion places ground claims within the instruction/direction and compensation framework, reinforcing the book’s recurring theme: procedure is substance in construction contracts.
Chapter 7: Valuation of Variation Claims — page 295
Chapter 7 answers the question Chapter 5 leaves open: once a variation exists, how much is it worth? This chapter is essential because entitlement without valuation is commercially incomplete.
Valuation Provisions — page 295.
The book reviews fair or reasonable sums, cost-plus valuation, price-based valuation, triggers, agreed valuation, and predetermined levels of varied work. It wisely notes that “fair valuation” can be uncertain and may be influenced by bargaining position unless disciplined by contract rules.
Operation of Price-Based Valuation Rules — page 297.
This section explains valuation at contract rates, adjusted contract rates, and fair valuation. The most important legal question is whether the varied work is sufficiently similar to original work to justify using existing rates.
Valuation of Omissions — page 308.
Omissions are not merely negative additions. Removing work may affect overhead recovery, profit, sequencing, and preliminaries. The book explains when contract rates apply and when adjustment may be needed.
Valuation of Preliminaries — page 312.
The subsections on approach, heads of preliminaries, quantity-dependent items, time-dependent costs, unrelated items, and unpriced items are extremely practical. Many claims fail because parties treat preliminaries as a lump rather than distinguishing their cost behaviour.
Overheads and Profit Considerations — page 316.
The discussion separates similar work, dissimilar work, and fair valuation. The core idea is that profit and overhead recovery must be justified, not assumed.
Commentary on SIA Provisions — page 318.
The SIA analysis is detailed: measurement, general valuation character, make-up of prices, preliminaries classification, contract rates, exact equivalent, commercial profitability, concurrent preliminary adjustment, rate adjustment, fair valuation, last-resort valuation, reduced profitability, accidental errors, and loss of profit. This is one of the book’s most technical and useful sections.
Chapter 8: Payments and Certification — page 335
Chapter 8 deals with cash flow, certification, and certifier independence. In construction law, this is not a side issue; cash flow is often the life of the project.
Employer’s Obligation to Pay — page 335.
The section distinguishes payment arrangements, lump-sum or entire contracts, and interim payments. The book explains why modern construction contracts need interim payment machinery: contractors cannot usually finance the whole project until completion.
Interim Certificates — page 337.
This section explains certification nature, process, commencement, certifying party, valuation, and legal effect. The certificate becomes both an administrative and legal instrument.
Other Payment Certificates — page 342.
The chapter covers final certificates, retention money, and other certification issues. These are important because final account disputes often involve whether a certificate has binding or temporary effect.
Position of the Certifier — page 347.
This is the chapter’s doctrinal heart. The certifier may be appointed by the employer but must act fairly and independently when certifying. The book discusses the Superintending Officer and the architect’s position as certifier, noting the importance of uninfluenced professional judgment.
Remedies for Wrongful Certification — page 355.
The section explores what happens when certification is wrong, delayed, or improperly influenced. The book’s treatment of Singapore authority is important: the owner is generally not liable simply because the certifier wrongly exercises independent judgment, absent interference or other exceptional circumstances.
Commentary on SIA Provisions — page 358.
The SIA discussion includes temporary finality, enforceability of certificates, set-off, review, and revision. The chapter is essential to understanding how the SIA form protects contractor cash flow while preserving final dispute resolution.
Chapter 9: Time-Related Claims — page 376
Chapter 9 is the principal delay chapter. Its central theme is that time provisions must reconcile three things: contractor responsibility, employer prevention, and liquidated damages.
Contract Provisions Relating to Time — page 376.
The subsections include express conditions, commencement, progress, reasonable dispatch, regular and diligent progress, intention not to be bound, implied provisions, and completion. These explain how time obligations arise even before delay claims are assessed.
Time of the Essence of Contract — page 383.
The book explains when time is of the essence and when time may be set at large. This is crucial because if employer prevention invalidates the liquidated damages machinery, the employer may lose the contractual delay remedy and be left to general damages.
Liquidated Damages and Penalties — page 386.
This section explains the nature of liquidated damages, penalty doctrine, the Dunlop principles, labels, relationship to breach, uncertainty, structure, trigger date, written demand, and missing rates. It is doctrinally strong and practically necessary.
Extensions of Time — page 396.
The chapter discusses the significance of extensions, standard form provisions, JCT, PSSCOC, ICE, PAM, acts of prevention, interpretation, common law, standard form drafting, nominated subcontractors, certification timing, strict and flexible approaches, and standard-form impact. This is one of the book’s densest and most important sections.
Grounds for Extension of Time — page 416.
The book examines force majeure, variations, adverse weather, meteorological data, late possession, nominated subcontract works, statutory changes, and related grounds. It treats EOT not as generosity to the contractor but as machinery preserving the employer’s right to liquidated damages.
Liability for Multi-Event Delays — page 430.
Concurrent delay is one of the hardest issues in construction law. The section considers multiple causes and how responsibility should be allocated where employer and contractor delays overlap.
Suspension of Works — page 435.
Suspension may arise from contractual right, employer default, non-payment, or instruction. The section is important because suspension can itself become a breach if wrongly exercised.
Acceleration Claims — page 440.
The book distinguishes acceleration requested by employer, acceleration undertaken to avoid liquidated damages, and acceleration where EOT has not yet been certified. It warns that acceleration costs require careful proof and often a supplementary agreement.
Commentary on SIA Provisions — page 448.
The SIA treatment addresses programmes, notification, extensions, delay certificates, completion certificates, and the consequences of the SIA structure.
Chapter 10: Computation of Time-Related Claims — page 469
Chapter 10 is the quantum counterpart to Chapter 9. It explains how delay and disruption claims are calculated.
General Approach — page 469.
The chapter begins with direct loss and expense, standard form provisions, computational framework, and heads of claims. The legal premise is tied to Hadley v Baxendale: claimed losses must flow naturally from breach or prevention.
Additional Expenditure — page 472.
This covers principal components, double handling, preparatory work, subcontract cancellation, and cost computation. These are the concrete costs caused by delay or disruption.
Interest and Financing Charges — page 474.
The book discusses context, common-law limits, exceptions, court powers, contract provisions, proof, simple and compound interest, and examples. Financing is treated as real construction loss, not an afterthought.
Loss of Productivity — page 487.
The subsections on typical situations, proof, learning curve, and examples are especially useful. Productivity loss is often asserted but difficult to prove; the book rightly insists on evidence.
Allowances for Inflation — page 492.
The section explains compensation principles, fluctuations clauses, adjustment mechanisms, price indices, JCT, ICE, and examples. Inflation matters because prolonged works can alter cost assumptions.
Site Overheads — page 497.
This covers components, classification, plant, equipment, examples, and method-related charges. The chapter carefully distinguishes site overheads from head office overheads.
Head Office Overheads and Profit — page 503.
The book covers the legal position, common-law approach, United States approach, components, profit, general principles, examples, Hudson formula, Eichleay formula, limitations, termination-related overheads, defences, and exculpatory clauses. It treats formulae as aids, not substitutes for proof.
Commentary on SIA Provisions — page 519.
The SIA section notes limits on architect certification of prolongation costs, contractor price make-up, and interest/finance charges. This is important because it distinguishes certifiable contract sums from claims requiring adjudication or arbitration.
Chapter 11: Performance Bonds — page 524
Chapter 11 is one of the book’s most distinctive Singapore-law chapters.
Introduction — page 524.
The book explains the nature of bonds, party relationships, and types of bonds and guarantees. Performance bonds are securities for performance and risk allocation, commonly required as contract conditions.
Characteristics of Conditionality — page 526.
The distinction between conditional and unconditional bonds is fundamental. Conditional bonds require proof of default or satisfaction of conditions. Unconditional demand bonds are payable on demand according to their terms.
Restraints on Calls of Bonds — page 530.
The book explains fraud as the traditional restraint and then turns to Singapore’s departure from English common law.
Doctrine of Unconscionability in Singapore — page 532.
This is the chapter’s centre. The book discusses Bocotra, definition of unconscionability, Unitrack, partial restraint, and other jurisdictions. Singapore law recognises fraud and unconscionability as independent grounds for restraining calls, but the threshold is strict and mere allegation is insufficient.
Practice Notes — page 547.
The book summarises principles and case situations. This is valuable because bond disputes are often urgent interlocutory matters.
Locus Standi of the Obligor — page 549.
The section addresses who has standing to object, especially where the contractor drops out. This is a precise and practical issue often overlooked in general texts.
Chapter 12: Claims Arising from Termination — page 555
Chapter 12 studies one of the most dangerous events in a construction project: termination. The chapter is strong because it separates common-law repudiation from contractual termination machinery.
Introduction — page 555.
The chapter sets the stage: termination is not merely ending the relationship; it triggers possession, payment, completion, damages, and sometimes bond calls.
Termination for Breach — page 555.
The book covers breach of condition, repudiation, rules of construction, onus of proof, and recourse. Termination must be justified, or the terminating party may itself be in repudiatory breach.
Contractor’s Right to Terminate — page 570.
The book discusses refusal of possession, prevention, non-payment, under-certification, and standard form provisions. This is important because contractors often assume non-payment gives an automatic right to walk away; the book is more careful.
Employer’s Right to Terminate — page 577.
The section covers grounds, time of the essence, warnings, and standard forms. Employers must comply strictly with notice and certificate requirements.
Unsatisfactory Progress of Works — page 582.
The section considers common-law and contractual grounds for terminating where progress is poor. It shows why “regularly and diligently” language matters.
Determination on a Party’s Insolvency — page 586.
Insolvency raises special issues because contract clauses must interact with insolvency law and distribution rules.
Repossession of Site by the Employer — page 589.
This is practically crucial. Once termination occurs, site possession, plant, materials, security, and completion become immediate problems.
Payments following Determination — page 598.
The section explains withheld payments and post-termination accounting. It is linked directly to Chapter 13.
Notification Requirements — page 601.
Notice provisions are treated as essential. Failure to comply can invalidate termination.
Commentary on SIA Provisions — page 606.
The SIA commentary covers termination without default, employer termination, contractor default, insolvency, possession, effects, contractor termination, suspension, and related procedures. The book gives a clause-sensitive account rather than a generalised one.
Chapter 13: Matters following Termination — page 623
Chapter 13 is a practical continuation of Chapter 12. It asks: after termination, how are the works completed and accounts settled?
The Completion Contract — page 623.
The book explains the decision to complete, completion cost components, arranging the completion contract, placing the contract, documents, cost determination, computation, contract rates, and increased variation prices. Its central point is that the employer must define what remains to be completed and separate completion costs from new or changed work.
Liability for Liquidated Damages — page 627.
The section considers common law and standard forms. The issue is whether liquidated damages continue after termination or whether general damages apply.
Funds Available to Meet Termination Costs — page 629.
The book covers withheld payments, retention sums, bonds, and insurance. It shows how project security is marshalled after termination.
Final Account: Example 1 — page 631.
The example illustrates how the employer calculates completion costs, previous payments, liquidated damages, and bond proceeds.
Termination on Employer’s Default — page 634.
The book explains the contractor’s claim components: value of work, materials, demobilisation, protection, plant, loss, profit, and overheads.
Final Account: Example 2 — page 638.
The second example illustrates contractor-side accounting after employer default.
Commentary on SIA Provisions — page 639.
The SIA discussion covers employer arrangements, withholding payments, temporary buildings, plant, materials, subcontractors, contractor arrangements, protection of works, removal of temporary works, and loss/expense.
Chapter 14: Sub-contractor and Suppliers — page 646
Chapter 14 addresses the layered nature of construction contracting. It is indispensable because many disputes involve parties who are not the employer or main contractor.
The Sub-contracting Process — page 646.
The book begins by explaining how subcontracting operates within the main contract structure.
Nominated Sub-contractors and Suppliers — page 651.
Nomination is legally delicate because the employer or architect selects a party, but the main contractor may remain responsible for performance.
The Employer and Sub-contractor — page 653.
This section examines whether and how the employer can have rights against subcontractors, including collateral warranties and third-party rights.
The Main Contractor and Sub-contractor — page 663.
The book explains direct contractual duties between main contractor and subcontractor, including payment, coordination, and responsibility.
Issues Arising from Nominated Sub-contracts — page 669.
This is the chapter’s practical centre. Nominated subcontracting creates risk misalignment: the main contractor may be responsible for a subcontractor it did not freely choose.
Objection to a Nomination — page 679.
The book explains when a contractor may object, for example due to capacity, terms, or reliability.
Dropping out by Nominated Sub-contractors — page 684.
This section considers what happens when nominated firms fail, withdraw, or are terminated.
Payments to Sub-contractors — page 692.
The book discusses “pay when paid” arrangements and their difficulties. Under the SIA context, subcontractor payment can depend on employer payment to the main contractor, creating cash-flow concerns for subcontractors.
The Contracts (Rights of Third Parties) Act — page 701.
This section evaluates statutory reform of privity and how third parties may enforce contract terms.
Commentary on SIA Provisions — page 706.
The SIA commentary covers designated and nominated subcontractors, objections, payment terms, sanctions, dropping out, and architect intervention.
Chapter 15: Claims under Negligence — page 721
Chapter 15 is the main tort chapter. It is especially valuable because construction disputes often straddle contract and tort.
General Principles — page 721.
The chapter begins with the nature of negligence and essentials of the action: duty, breach, causation, and loss. It explains negligence as failure to exercise legally required care.
Duty of Care — page 722.
The book explains existence, extent, and construction application. This is crucial because not every careless act in construction creates liability to every affected party.
Liability for Statements — page 724.
The Hedley Byrne principle is central. Negligent statements, reports, soil information, and certifications can cause economic loss.
Liability for Building Defects — page 727.
The book traces development beyond Donoghue and Hedley Byrne, Dutton, Anns, damage to buildings, and absence of actual damage. It explains how building defects challenged traditional negligence limits.
Recovery of Economic Loss — page 735.
This section considers Junior Books, contractual recourse, and the contract/tort boundary. It is one of the most theoretically important sections.
Revolt against Anns in England — page 740.
The discussion of D & F Estates and Murphy explains the English retreat from expansive negligence liability for building defects.
Position in Other Jurisdictions — page 751.
The book compares New Zealand, Canada, and Australia, showing that common-law jurisdictions did not move uniformly.
The Position in Singapore — page 755.
The book’s Singapore discussion is central. It reviews Ocean Front and Eastern Lagoon, and the impact of Singapore’s approach to economic loss and building defects.
The Position in Malaysia — page 764.
The book adds regional comparison and shows that Malaysian law must be understood separately.
Liability of Parties to Contractors — page 765.
The section examines owners, consultants, negligent statements, design, supervision, certification, and other liability areas. It is a useful reminder that contractors may sometimes sue consultants despite no direct contract.
Position of Sub-contractors — page 786.
The book discusses subcontractor duty of care, Hedley Byrne liability, and tort relationships with main contractors.
Concurrent Liability — page 789.
This section examines when contract and tort liability may coexist.
Limitation of Actions — page 790.
The chapter ends with limitation periods, fraud, concealment, negligence, and defects. This is essential because defect claims often arise years after completion.
Commentary on SIA Provisions — page 793.
The SIA commentary covers methods of working, temporary works, permanent works, certification, injury, property damage, and insurance.
Chapter 16: Construction Litigation — page 802
Chapter 16 turns from substantive law to dispute procedure. It is selective rather than a full civil procedure textbook, focusing on construction-specific litigation strategy.
Introduction — page 802.
The chapter situates litigation within construction disputes and notes that arbitration is often preferred, though litigation remains important.
Characteristics of Construction Litigation — page 803.
The book stresses complexity: extra work, valuation, delay, nominated subcontractors, technical documents, and expert evidence often combine in one dispute.
Commencement of Litigation — page 804.
The sections on writ and appearance explain how construction claims begin in court.
Pleadings — page 805.
Statement of claim, defence, counterclaim, reply, and close of pleadings are covered. Construction pleadings must be precise because claims are fact-heavy and document-heavy.
Particulars and Discovery — page 809.
The book explains particulars, further particulars, discovery, discoverable documents, privilege, and redactions. This is vital because construction cases are often won or lost on records.
Determining the Party to Sue — page 812.
The book examines claims involving employers, contractors, consultants, subcontractors, suppliers, liquidators, and third parties. This is important in multi-party projects.
Third Party Proceedings — page 817.
Construction disputes often require contribution, indemnity, or pass-through claims; this section explains that procedural mechanism.
Summary Judgment — page 818.
This is important in payment disputes, especially where certificates have temporary finality.
Order for Interim Payment — page 827.
The section covers when interim payment may be ordered before final judgment.
Stay of Proceedings — page 829.
This section explains arbitration clauses, readiness and willingness, valid arbitration agreements, and refusal of stay.
Security for Costs — page 834.
The book explains how defendants may protect themselves against impecunious plaintiffs.
Records and Documentation — page 836.
The section is one of the chapter’s strongest. It covers minutes, site diaries, drawings, programmes, document analysis, and claim management. The book rightly warns against launching claims before documents are properly studied.
Witness and Expert Evidence — page 843.
Construction litigation depends heavily on expert evidence in defects, delay, and payment disputes.
Dismissal of Action — page 849.
This section covers procedural default and deemed discontinuance.
Global Claims — page 849.
The book addresses particularisation problems. Global claims are attractive to claimants but vulnerable if they fail to connect cause and loss.
Costs — page 852.
Costs, payment into court, offers to settle, set-off, counterclaim, and admissions are reviewed.
Enforcement of Judgment — page 859.
The book briefly covers turning judgment into recovery.
Settlement — page 859.
The section considers settlement factors, partial settlement, and documentation.
Commentary on SIA Provisions — page 861.
The SIA discussion returns to temporary finality, summary judgment, set-off suspension, interest, and certificate review.
Chapter 17: Arbitration — page 870
Chapter 17 presents arbitration as the traditional construction dispute forum.
Introduction — page 870.
The chapter defines arbitration as private adjudication by a chosen tribunal rather than the court.
The Arbitration Agreement — page 874.
This section covers incorporation, ambit, and validity. The book correctly stresses that arbitration clauses require clear incorporation, especially in construction documents with multiple standard terms.
Commencement of the Reference — page 879.
The chapter explains how arbitration begins and why timing matters.
Appointment of Arbitrator — page 881.
The book discusses appointment methods, party choice, institutional appointment, impartiality, and practical confidence in the arbitrator.
The Arbitrator’s Powers — page 886.
This section reviews procedural and substantive powers, including control of proceedings and interim issues.
Arbitrator’s Jurisdiction — page 889.
Jurisdiction is central: an arbitrator may only decide matters within the arbitration agreement and statutory authority.
Security for Costs — page 891.
The arbitration analogue to court security is addressed.
Powers under the Standard Forms — page 893.
This section links arbitration powers to construction forms, including SIA and other standard forms.
Pre-Hearing Matters — page 900.
The book covers pleadings, statements, timelines, issues, discovery, amendments, interlocutory matters, procedure, and delay.
The Hearing — page 905.
Oral hearing, hearing dates, submissions, order of proceedings, counterclaims, evidence, experts, and record are covered.
The Award — page 910.
The book explains interim and final awards, form, substance, decision completeness, certainty, consistency, consent awards, and reasons.
Award of Interest — page 915.
The tribunal’s power to award interest is treated as commercially significant.
Costs of Arbitration — page 917.
The section covers cost components, power to award costs, factors, and sealed offers.
Challenge of Awards — page 920.
Appeal, setting aside, court powers, and grounds are discussed.
Removal of an Arbitrator — page 923.
The book covers incapacity, delay, improper conduct, and consequences.
Effect of a Valid Award — page 926.
Finality, correction, enforcement, and the arbitrator’s post-award position are explained.
Commentary on SIA Provisions — page 928.
The SIA discussion covers scope, powers, rectification, interest, restrictions, variation claims, quantities, EOT, partial occupation, certificates, procedure, timing, appointment, and rules.
Chapter 18: Preparation and Negotiation of Claims — page 937
Chapter 18 is a fitting final chapter because most construction disputes settle before formal adjudication. It treats claim preparation as both legal and commercial work.
Introduction — page 937.
The book states that most construction claims settle without court or arbitration. That is a realistic and important starting point.
Preparation Issues — page 937.
The subsections include procedural compliance, formulation, preliminary analysis, and use of claims consultants. The main lesson is that claims should be prepared with litigation or arbitration in mind, even when settlement is expected.
Viability of a Claim — page 941.
The book examines claim character, party to sue, legal premise, facts, witnesses, experts, timing, implications, counterclaim, and resources. This is excellent legal-method training: entitlement, evidence, and economics must all be tested.
Post-Submission Negotiations — page 947.
The book discusses negotiation scope, team, mandate, dealings with the other party, process management, offers, counteroffers, and settlement. The emphasis on mandate is practical: negotiators without authority waste time.
Preparation of Supporting Materials — page 951.
This section covers gathering facts, locating costs, delay/disruption claims, document analysis, legal issues, project personnel, settlement probability, future relationship, survival capacity, and commercial interests.
The Claim Submission — page 957.
The book explains outline, project description, factual analysis, contract provisions, and compensation computation. It treats claim submission as a serious legal document even when styled as a business letter.
Negotiation — page 960.
The section covers negotiation nature, conceptual framework, competitive negotiation, cooperative negotiation, interest-based negotiation, Putnam model, stages, objectives, research, agenda, solutions, settlement, and agreement. The book’s preference for interest-based negotiation is sound because construction parties often need future working relationships and creative commercial solutions.
Postscript: Public Sector Standard Conditions of Contract — page 972
The postscript is more than an add-on. It captures a shift in Singapore public-sector contracting practice.
Introduction — page 972.
The book explains the background, industry consultation, impending security-of-payment legislation, and areas of change. It says the newer PSSCOC moves toward a more balanced risk allocation structure compared with earlier owner-favouring forms.
Unforeseen Sub-Surface Conditions — page 973.
The postscript discusses geotechnical information, exclusion of liability, adverse physical conditions, time and cost recovery, underground services, and foreseeability. This directly updates Chapter 6’s ground-risk discussion.
Claims for Variations — page 979.
The section reviews general changes, substantial completion of variation work, timelines, and valuation differences.
Progress Payments — page 981.
This section discusses certification until final accounts and reduced payment-processing periods. It connects to the broader policy of improving cash flow.
Final Account Procedure — page 983.
The book covers interim final account, final account, defects liability, reduced settlement time, payment information display, and cross-claims. The legal significance is that final-account machinery is treated as an administrative discipline, not merely a post-project formality.
Appendices
Appendix 1 — page 989.
This contains the SIA Articles of Agreement and Conditions of Contract. Its inclusion is important because much of the book’s commentary depends on the SIA contractual architecture, especially temporary finality, architect’s certificates, variation instructions, termination, and arbitration.
Appendix 2 — page 1057.
This contains the Singapore Public Sector Conditions of Contract. It complements the postscript and allows readers to connect commentary to actual contract text.
Index — page 1125.
The index is unusually valuable because the book is dense and cross-referential. Topics like performance bonds, temporary finality, quantum meruit, site conditions, termination, and negligence recur across multiple chapters.
Final evaluation
As a law professor, I would assign this book not as light reading, but as a serious professional text. Its major virtues are doctrinal precision, practical realism, careful treatment of standard forms, and strong attention to Singapore construction law. It is especially valuable for understanding how claims are generated and defended.
The book’s highest contribution is its explanation of construction law as administered law: rights are not found only in abstract principles, but in notices, certificates, valuation clauses, programmes, drawings, bills, bonds, subcontracts, and procedural steps. A contractor may have a morally strong claim and still fail through lack of notice or proof. An employer may have a genuine complaint and still lose a termination argument through defective procedure. A certifier may be appointed by the employer yet must act independently. A performance bond may be intended as ready security yet still be restrained where the call is abusive.
Its central warning to lawyers and construction professionals is this: construction disputes are rarely caused by one legal rule. They are produced by the interaction of drafting, pricing, risk allocation, administration, evidence, and timing. That is why the book remains valuable as both a legal treatise and a practical guide to construction claims.