PROPERTY CASES > L v H 0008 - Sale of land -- Date for completion -- Time not of the essence -- Whether purchaser liable in damages for non-completion -- Whether vendor ready, willing and able
L v H 0008 - Sale of land -- Date for completion -- Time not of the essence -- Whether purchaser liable in damages for non-completion -- Whether vendor ready, willing and able
Description
SUPREME COURT OF NEW SOUTH WALES -- COURT OF APPEAL
Giles, Fitzgerald and Heydon JJA
12, 24 July 2000
-- Sydney
[2000] NSWCA 182
Sale of land -- Date for completion -- Time not of the essence -- Whether purchaser liable in damages for non-completion -- Whether vendor ready, willing and able -- Intimation of non-performance and dispensation from performance.
A contract for sale of land was in the form of the 1988 edition and provided for settlement within 6 weeks, 1 November 1989. The appellant as vendor claimed common law damages for non-completion by the respondents.
Young J held that the appellant in such an action had the onus of proof in showing compliance with all conditions precedent. Since the appellant could not establish that the failure to complete occurred without blame on her part, her action for damages must fail.
In due course, the property was sold by the vendor's mortgagee under power of sale to the respondents.
On appeal, the appellant submitted in terms of ground 10 of the notice of appeal, that it was understood between the parties that the contract was due to be completed on 1 November 1989 and thereafter the appellant could remain in possession rent free until 8 December 1989 and thereafter as a licensee.
Held, by Giles and Heydon JJA:
(i) The evidence disclosed an intimation by the appellant that she would not be able to deliver vacant possession on or after 8 December 1989 as the agreement between the parties required.
(ii) The intimation was delivered before 1 November and the respondents were accordingly absolved from tendering performance on 1 November and were not in breach of the obligation to complete on that date.
Foran v Wight (1989) 168 CLR 385 ; 88 ALR 413, applied
Per Fitzgerald JA: Once 8 December passed without lawful termination of the contract by either party, it remained on foot for the benefit of both parties. The appellant remained liable to deliver vacant possession after 8 December which she was unwilling to do and later became unable to do because of the mortgagee's sale.
The appellant did not prove that either her loss of the contract or any consequential loss was caused by any breach on the part of the respondents.